Procurement template: receiving inspection

Receiving Inspection Checklist for Aerospace Parts

A receiving inspection checklist is the numbered list a dock inspector works through on every delivery: packaging, paperwork match to the PO, marking and IUID, quantity, condition, shelf life, ESD handling, material cert review against the specification, sampling, dimensional checks, quarantine and records. Copy it into your procedure and cite failures by line number.

Updated

How to use this checklist

Work the checklist top to bottom on every receipt, record accept, reject or not applicable on each numbered line with the inspector's stamp and date, and move anything that fails into quarantine before you do anything else. Paperwork is checked before the parts, because a lot that cannot be traced cannot be accepted however good it looks.

The receiving inspection guide explains why receiving exists and how MRB works. This page is the working list: numbered lines a buyer can copy into a receiving procedure or traveler and cite as "line 23". Delete lines that do not apply to the commodity, and add the requirements on your own PO.

A. Shipment and packaging, before opening

Inspect and photograph the outside of the shipment first. Packaging evidence disappears the moment the box is opened.

#Field / clauseWhat to enter or requireWhy it matters / reference
1Carrier paperworkBill of lading or airbill matches the PO, piece count and any damage noted on the delivery receiptSupports a carrier claim; note damage before signing
2SealsTamper-evident seal numbers match the packing list and are unbrokenChain of custody for flight hardware; see shipping flight hardware
3Shock, tilt and temperature indicatorsRecord the state of each indicator; photograph any activated oneAn activated indicator is grounds to hold and inspect, not to reject outright
4Humidity indicator cardRead the card through the bag window and record the readingWet desiccant means the barrier failed
5Packaging levelPackaging and preservation match the PO, for example MIL-STD-2073-1 methods where invoked (confirm the current revision on ASSIST)See crating and packaging
6Cleanroom and cleaned itemsDouble bag intact; do not open outside the cleanliness level the PO requiresOpening at the dock voids a precision clean; see precision cleaning
Have a part like this?Send it in under a minute. A person replies within 1 business day.

B. Paperwork match

Every document must carry the same part number, revision and lot as the parts in the box. A correct cert for a different lot is not evidence for this one.

#Field / clauseWhat to enter or requireWhy it matters / reference
7PO and linePacking slip quotes the PO number and line itemTies the receipt to the contract requirements
8Part number and revisionExact match across PO, packing slip, C of C, labels and parts, including dash numberThe most common hold; one character matters
9Certificate of conformanceSigned by an authorized person; states PO, part number, revision, quantity, lot or serial numbers and the specifications metSee certificate of conformance
10Material certificationsPresent for each heat or lot, traceable to the parts; reviewed in section GSee material certs and traceability
11Special process certificationsOne cert per process naming the specification, revision, type or class, and the processorMust match the process sources the PO allows
12First articleAS9102 report with the first shipment when required, or a reference to the approved FAIRSee AS9102 first article inspection
13Test reportsAcceptance test, pressure test, NDT or functional test reports the PO calls forResults must reference the serial or lot shipped
14Specialty metals and originDFARS specialty metals compliance statement or melt country where the PO requires itSee DFARS specialty metals
15Source inspection evidenceGovernment source inspection stamp or signature, or customer source acceptance, when the PO requires itParts shipped without required source inspection cannot be accepted at destination
16Deviations and waiversApproved deviation or waiver attached for anything shipped not to drawingNo approval on file means nonconforming

C. Identification, marking and IUID

Check that each item is identified the way the drawing says, and that the marks agree with the paperwork.

#Field / clauseWhat to enter or requireWhy it matters / reference
17Part markingContent, method and location per the drawing; no marks on prohibited surfacesSee part marking and labels
18Lot and serial numbersMarked numbers match the C of C and test reports; no duplicate serialsTraceability starts here
19IUID required?Check the contract for DFARS 252.211-7003: items with a government unit acquisition cost of $5,000 or more, plus any items listed in the schedule or attachmentsDFARS 252.211-7003 (Jan 2023), paragraph (c)(1)
20IUID mark2D Data Matrix present, readable with a verifier, and its UII matches the paperworkThe clause calls for marking to MIL-STD-130, latest version, unless the contract cites one
21Container labelsShipping and storage labels to MIL-STD-129 when the contract invokes itLabels carry the dates and identifiers receiving records

D. Quantity and condition

Count, then look. Condition defects found later in assembly are expensive to trace back to the delivery.

#Field / clauseWhat to enter or requireWhy it matters / reference
22QuantityCount against the packing slip and PO; record over or short shipmentOver-shipments still need a decision before stock
23Handling damageDents, scratches, bent pins, damaged threads, crushed tubing endsPhotograph before moving the part
24Finish and corrosionCoating present, uniform and undamaged; no corrosion, staining or bare edgesSee surface finishing
25Foreign object debrisChips, burrs, loose hardware or debris in bores, ports and packagingSee FOD prevention
26Port and thread protectionCaps and plugs installed on fluid ports and connectorsSee caps and plugs

E. Shelf life and cure dates

Read the dates on every unit and compute remaining life against the PO minimum before the material goes to stock.

#Field / clauseWhat to enter or requireWhy it matters / reference
27Dates presentDate of manufacture or cure date, and expiration or inspect/test date, on each unitMIL-STD-129R marks elastomer cure dates by quarter, for example 4Q13
28Remaining shelf lifeRemaining life at receipt meets the PO minimumShort-dated material is a nonconformance, not a bargain
29Cold chainCoolant present and temperature indicator not tripped for frozen or refrigerated items; move to storage firstSee shelf life control
30Batch traceabilityBatch number on container matches the certificate or test reportDates mean nothing without the batch link

F. ESD-sensitive items

Electrostatic discharge damage is invisible at receiving, so control the handling rather than inspect for the damage.

#Field / clauseWhat to enter or requireWhy it matters / reference
31ESD packagingItems arrive in ESD protective packaging, closed and markedANSI/ESD S541 covers packaging for ESD-sensitive items; confirm the current revision with the ESD Association
32Where to openOpen only at an ESD protected workstation by trained staffANSI/ESD S20.20-2021 sets the ESD control program requirements
33RepackagingReturn items to ESD packaging before they leave the protected areaUnprotected transfer is where most handling damage happens

G. Material cert review against the specification

Compare the cert to the specification and PO, line by line. Do not accept a cert because its own "spec" column says "pass".

#Field / clauseWhat to enter or requireWhy it matters / reference
34Specification and revisionMaterial specification and revision on the cert match the PO and drawingAn older revision may have different limits
35Alloy, temper, condition, formAlloy, temper or heat treat condition, product form and size matchWrong temper is a common, invisible error; see aluminum alloys
36Heat or lot numberHeat or lot on the cert matches the marking on the material or partsBreaks in this link void traceability
37ChemistryEach element within the specification limits for that alloyCheck against the spec table, not the cert's summary
38Mechanical propertiesTensile, yield, elongation and hardness meet the spec for the form, size and direction testedMinimums often vary by thickness and grain direction
39Source and signaturesMill or test lab identified, report signed or authenticated, lab accreditation where the PO requires itDistributor-retyped certs need the original mill cert behind them
40Verification testHardness, conductivity or PMI where the risk or PO calls for itCatches mixed stock and wrong alloy

H. Sampling

Use the sampling plan your procedure or customer specifies, and default to accept-on-zero for aerospace characteristics. ANSI/ASQ Z1.4 is the common attribute sampling system and descends from MIL-STD-105E; its AQL plans can accept lots with defects in the sample. Zero acceptance number (c=0) plans, published by Nicholas Squeglia (Zero Acceptance Number Sampling Plans, 5th edition, 2008), reject the lot on any defect. As a published worked example, a lot of 250 at an AQL of 1.5 calls for 19 pieces inspected with zero defects.

#Field / clauseWhat to enter or requireWhy it matters / reference
41Plan and levelName the plan (Z1.4 level and AQL, or c=0 table and index) on the receiving recordCustomer clauses override defaults; some primes publish their own, such as RTX ASQR-20.1
42Statistical checkFor a confidence C that the lot defect rate is below p, sample n = ln(1 minus C) divided by ln(1 minus p) with zero failures95 percent confidence of under 5 percent defective needs 59 pieces; under 1 percent needs 299
43100 percent itemsKey characteristics, safety critical features and anything not inspectable after assemblyOr verified process capability data from the supplier
44SwitchingTighten after a rejection, relax only after a defined clean historyRecord the switch and why

I. Dimensional and functional checks

Measure the features that matter most and the ones most likely to be wrong.

#Field / clauseWhat to enter or requireWhy it matters / reference
45Characteristic selectionKey characteristics, features flagged on the FAIR, and features with a history of escapesTargets the sample where risk is
46Measurement capabilityGage resolution and uncertainty small enough to decide the toleranceSee inspection and metrology
47Threads and fitsGo and no-go thread gages, pin gages and mating checksQuick checks that catch common machining errors
48Functional and cleanliness checksFit, function, leak or cleanliness level where the PO specifies themFor fluid parts, compare to the specified level; see the fluid cleanliness code tool

J. Counterfeit-risk items

Electronic parts and other high-risk items need source evidence before any test result means anything.

#Field / clauseWhat to enter or requireWhy it matters / reference
49SourceOriginal manufacturer, authorized distributor, or a source approved under your counterfeit planDFARS 252.246-7008 (Jan 2023) sets that order for electronic parts
50Traceability documentsManufacturer C of C and the chain of custody back to the original manufacturerThe same clause requires tracking from the original manufacturer to acceptance
51Physical indicatorsMarking quality, date and lot codes consistent across reel or tube, signs of resurfacing or remarkingSAE AS5553 covers detection for EEE parts
52Suspect counterfeitQuarantine, report through your process and GIDEP; do not return to the sellerDFARS 252.246-7007; see counterfeit parts avoidance

K. Quarantine and nonconformance path

Any "reject" above starts the same path: identify, segregate, record, disposition.

#Field / clauseWhat to enter or requireWhy it matters / reference
53Identify and segregateReject tag on the item and move it to a controlled hold area the same dayPrevents use in production
54Nonconformance reportNCR with the line number failed, measurements, photos and the paperwork reviewedEvidence the supplier and MRB can act on
55Disposition authorityReturn, rework or scrap by quality; use as is or repair only through MRB with design authority approvalSee corrective action and SCARs
56Supplier notice and SCARNotify the supplier with the NCR; issue a SCAR for repeat or systemic issuesFixes the cause, not only the lot
57Containment checkCheck stock and work in process from the same lot, heat or shipmentOne bad lot often has siblings

L. Records

Keep a receiving record that someone can use years later to find every affected part.

#Field / clauseWhat to enter or requireWhy it matters / reference
58Receiving recordPO, line, part number, revision, quantity, lot or serials, supplier, cert pack reference, results by line number, inspector and dateLinks the delivery to its evidence
59EvidencePhotos of packaging and indicators, measurement data, verifier reportsHard to recreate once packaging is discarded
60RetentionRetain for the period your contract and quality system requireSee records and change control
61Supplier performance feedRecord accept or reject per lot into supplier scorecardsSee supplier scorecards

How to adapt this checklist

  • Split it by commodity: machined parts, raw material, EEE parts and chemicals need different subsets. Keep the line numbers stable inside each version so NCRs can cite them.
  • Put the matching requirements on the PO. Receiving can only check what the PO asked for, so state the cert pack, FAI, packaging, IUID, shelf life minimum and sampling plan in the order. The RFQ builder helps put them in the request.
  • Tie supplier approval to it: new suppliers from the supplier survey questionnaire start on tightened inspection.
  • Have your own quality and contracts teams review it before use. It is a working template for buyers, not legal advice, and your quality system procedures control.

Get parts that clear this checklist

We flow these receiving requirements down to the supplier at order, check the cert pack against them before shipment, and deliver with a certificate package built to your PO. Request a quote and attach your receiving requirements; a person replies within 1 business day. For export-controlled hardware or data, read confidentiality first.

Quote this

Send the job. A person replies within 1 business day.

Part, quantity and date are enough to start. Drawings and the mutual NDA follow by reply, and controlled programs never send technical data through this site.

Export classification *

Need to attach drawings or sign the NDA first? Use the full request form.

Questions

What should a receiving inspection checklist include?

At minimum: shipment and packaging condition, paperwork match against the PO, part identification and marking, quantity, visual condition, shelf life dates, ESD handling, material cert review against the specification, a named sampling plan, dimensional checks on selected characteristics, a counterfeit check for high-risk parts, a quarantine path and a record. Each line should be numbered so a nonconformance report can cite exactly which check failed.

How many parts should receiving inspect?

Use the plan your procedure or customer clause specifies. Many aerospace buyers use zero acceptance number plans, where any defect rejects the lot; a published example is 19 pieces from a lot of 250 at AQL 1.5. A quick statistical check: 59 pieces with zero failures gives 95 percent confidence that the lot is under 5 percent defective. Critical characteristics usually need 100 percent inspection.

When does a delivered item need an IUID mark?

When the contract includes DFARS 252.211-7003. The January 2023 clause requires unique item identification for delivered items with a government unit acquisition cost of $5,000 or more, plus items listed in the schedule or its attachments, such as embedded parts or serially managed items. The mark follows MIL-STD-130 at the version the contract cites. Receiving checks that the Data Matrix reads and matches the paperwork.

Should receiving check material cert chemistry against the spec?

Yes. Compare each element and mechanical property on the cert to the limits in the specification and revision on the PO, for the form and size delivered. Do not rely on a pass statement printed on the cert. Also confirm that the heat or lot number on the cert matches the marking on the material, because a correct cert for another heat proves nothing.

What happens to parts that fail receiving inspection?

They are tagged, moved to a controlled hold area and written up on a nonconformance report. Quality can return, rework or scrap them; use as is and repair need the material review board with design authority approval. The supplier gets the NCR and, for repeat problems, a corrective action request. Suspect counterfeit electronic parts are quarantined and reported, never returned to the seller.

How is this different from your receiving inspection guide?

The guide explains what receiving inspection is for, what a cert pack contains and how nonconformances are dispositioned. This page is the line-by-line template: numbered checks with what to require and the reference behind each, including IUID, ESD, shelf life, cert-to-spec review and sampling math. Use the guide to train people and this checklist to run the dock.

Related

Sources

Ready to
source it?

A person replies within 1 business day. NDA first.

Request a quote